IDSUD Energies Africa to supply The Midelt Wind Farm with its Hybrid Solution, Nheolight

IDSUD Energies ’s Subsidiary in Africa to take part of The Midelt Wind Farm’s construction, by designing and dimensioning a Photovoltaic Power Plant with a capacity estimated at 32,4 kWc and a 22 kVA of diesel back-up capacity.

The following approach will supply them with more than 50 % of clean energy.

Hence, in order to light up pedestrian areas, Construction Management Services Company has chosen IDSUD Energies innovative hybrid solution Nheolight.

Thanks to its Hybrid combination (wind and solar) it provides a good quality lighting.

La société Construction Management Services (CMS) spécialisée dans la construction de grands projets structurés a choisi la société IDSUD ENERGIES AFRIQUE afin de couvrir les besoins énergétiques de sa base vie pour le développement du futur parc éolien dans la région de Midelt.

L’équipe IDSUD Energies Afrique a accompagné CMS à travers son bureau d’étude, pour concevoir et dimensionner une solution innovante par une centrale PV de 32,4 kWc couplé à un groupe électrogène de 22 kVA. Cette approche permet de fournir à la base plus de 50% en EnR propre.

Pour illuminer les voies piétonnes, le choix s’est porté vers 4 Nheolights hybrids doubles crosses qui par leurs combinaisons de production d’énergies (éolien et solaire) offre un éclairement au sol de qualité.